Proposed project Implementation plan and probable time table
for
Development of applicable package for the visually handicapped citizens
Activities |
Dec. 2002 |
Jan. 2003 |
Feb. |
Mar. |
Apr. |
May |
Jun. |
Jul. |
Aug. |
Sep. |
Oct. |
Nov. |
Dec. |
Jan. 2004 |
Literature Review |
x |
x |
|
|
|
|
|
|
|
|
|
|
|
|
Activating social interaction |
|
x |
x |
|
|
|
|
|
|
|
|
|
|
|
Identify the problems Education Social Economic (Self Employment) Cultural & Other activities |
|
|
x |
x |
|
|
|
|
|
|
|
|
|
|
The preparation of preventing measures to address the above problem. Small-scale sample survey to quantify these problems. Orientation programme to identify select the resource persons. Organizing participatory approaches to increase the precision of the data collection. Case studies, Rapid appraisal (PRA) survey, Group discussions. Analysis of available information and data. |
|
|
|
x
x |
x x
x |
x x
x |
x |
|
|
|
|
|
|
|
Preparation of action plan for operationalise the objectives of this project. Some useful suggestions to ensure sustainable and pragmatic implementation of above action plan as a applicable package. Distribution of apparatuses & equipment's to selected group. |
|
|
|
|
|
x
x
x |
|
|
|
|
|
|
|
|
Conducting 6 month's vocational Training programme for selected Trainees. (1st Batch 20Trainees) Performance Test. Course evaluation certificate awarding ceremony. |
|
|
|
|
|
|
x
|
x |
x |
x
|
x
|
x |
x |
x |
Cost Estimate's for the development of applicable package
|
Total Rs. |
Org. Rs. |
Participants Rs. |
Donors Rs. |
Income from Magazine |
1.1 Expenditure for literature review and secondary data & information (2 resource persons & 5 days x Rs. 500/= each)
1.2 Meeting expertise in the related fields (Physicians, professor's, university lecturers govt. officials) Traveling & Related expense
1.3 To sample survey & questionnaire (500 papers, postage, printing & processing) (100/= x 500)
1.4 Preparation of questionnaire (4 Resource persons x 5 days) (500/= x 4 x 5)
1.5 Other preparation Expenses. Labour charges & selection of Participants etc. (3 persons x 2 day x Rs 500/=)
2.1 Organizing orientation programme (Project Administration) (2 persons x two months (Rs. 5000/= each) April, May ) 2.2 Equipment Hiring charges 2.3 Tea & Meals for all participants including organisers Colombo 100/= x 70 = 7000/= Gam. 100/= x 70 = 7000/= Kalutara 100/= x 70 = 7000/=
2.4 Traveling allowance to participants (Rs. 200/= x 70 x 3 centers) (Including assistants)
Contd.,
(3) Distribution of apparatuses & equipment's for selected trainees & other resource persons. Equipment Nos cost per unit Total (Rs.) 3.1 White cane 100 200/= 20,000.00 3.2 Talking watches 50 300/= 15,000.00 3.3 Radio cassettes 20 3,000/= 60,000.00 3.4 Braille papers 50 500/= 25,000.00 3.5 Braille equipments 50 150/= 7,500.00
(4) Management fees
(5) Training courseAllowance for lecturers (Blind Teachers) 1st stage 5.1 (Rs. 500/= x 8 days x 3 person) 12,000.00 x 3 months 5.2 Performance assessment (Rs. 500/= x 3 x 2 day ) 2nd stage 5.3 3 persons x (2 days per week) 8 days x 3 months) x 500/= Final performance Assessment 5.4 (3 persons x 4 days x 500/= ) 5.5 Allowance for trainees (Rs 2500/= & participant as Travelling Allowance) (Rs. 2500/= x 20) (6) Other expensesTelephone Traveling & Transport Tea & Meal expenses Course evaluation, certificate awards & ceremony related expenses
|
5,000.00
5,000.00
5,000.00
10,000.00
6,000.00
30,000.00
28,000.00
2,000.00
4,000.00
21,000.00
42,000.00
87,000.00
20,000.00 15,000.00 60,000.00 25,000.00 7,500.00
127,500.00
25,000.00
36,000.00 3,000.00
36,000.00 8,000.00
50,000.00
10,000.00 15,000.00 15,000.00 25,000.00
465,500.00
|
5,000.00
5,000.00
5,000.00
10,000.00
6,000.00
30,000.00
28,000.00
-
-
-
12,000.00
12,000.00
20,000.00 - 20,000.00 - 7,500.00
47,500.00
-
12,000.00 3,000.00
12,000.00 8,000.00
-
10,000.00 5,000.00 - -
137,500.00
|
-
-
-
-
-
-
-
-
4,000.00
21,000.00
-
25,000.00
- - - - -
-
-
- -
- -
10,000.00 - -
- 10,000.00 -
45,000.00 |
-
-
-
-
-
-
-
2,000.00
-
30000.00
50,000.00
- 15,000.00 40,000.00 25,000.00 -
80,000.00
-
24,000.00 -
24,000.00 -
40,000.00
- 10,000.00 - 15,000.00
243,000.00
|
-
-
-
-
-
-
-
-
-
-
-
-
- - - - -
-
25,000.00
- -
- -
-
- - 5,000.00 10,000.00
40,000.00 |
|
Total/ Cost Estimates |
SHIA |
Participant
|
Other Donors |
New Magazine |
02 Computers 01 Administration 01 Training purpose
Type Writers Manual Writers Sinhala 05 No's English 05 No's
Braille Typewriters
Office Equipment Furniture & fittings Writing Table 03 x 4500/= Ward Robes 02 x 5000/= Study Table 02 x 8000/= |
75,000.00 125,000.00
40,000.00 48,000.00
160,000.00
13,500.00 10,000.00 16,000.00
487,500.00
|
- -
- -
160,000.00
- - -
160,000.00 |
- -
- -
-
- - -
- |
75,000.00 125,000.00
40,000.00 48,000.00
-
13,500.00 - 16,000.00
317,500.00 |
- -
- -
-
- - 10,000.00
10,000.00 |